When a supplier quotes a substitute: How to compare alternate materials in an RFQ

Back to Company Posts

Ask for the specified material and any substitute on separate quote lines. Then test whether the savings cover qualification costs and fit your schedule.

When a supplier quotes a substitute: How to compare alternate materials in an RFQ

Decide before you send a request for quotation (RFQ) whether suppliers may propose a different material. If the answer is yes, ask each bidder to price the specified material first and put any substitute on a separate line. If a supplier can quote only the substitute, ask it to say so. That gives you two distinct decisions: who offers the best price for the part as drawn, and whether a change is worth approving.

Tell suppliers what can change and what must stay fixed

Give every bidder the same drawing revision, order quantity, delivery address and required arrival date. Identify the specified material grade and finish, not just the material family. Then name the features that matter in use. For a panel that drops into an existing fixture, for example, finished thickness and flatness may matter more than surface appearance.

Ask the person responsible for the design which substitutions they can approve and which require customer consent. If the material is fixed by a customer drawing, mark it as mandatory unless you have permission to consider a change. Do not invite bidders to spend time developing an option you cannot buy.

Shortlist suppliers and give them one reply format

Use the Corplace directory of U.S. companies to identify potential suppliers. Before sending the full RFQ, ask each candidate whether it can work to the drawing, identify the exact grade it would supply and provide a finished sample for evaluation. Treat the listing as a starting point; confirm capabilities directly. When drafting the request, you can also browse public requests for quotation on Corplace for examples of how buyers describe their requirements.

Request these four items for each option:

  • Material and exceptions: Name the grade and finish. List every departure from the drawing, even if the supplier considers it an improvement.
  • Delivered price: Separate unit price, setup, sample charges, packaging and freight to the named destination. Mark exclusions rather than leaving blanks.
  • Schedule: State when a sample can arrive, when production can start after written approval and when the full order can reach your dock.
  • Quality evidence: Describe how the supplier will check the critical features and identify which material was used for the production lot.

Worked hypothetical: Is a $480 saving worth a material change?

Suppose a fabricator needs 400 panels. The specified version costs $18 per panel plus $320 freight, or $7,520 delivered. An alternate grade costs $16.80 per panel with the same freight, or $7,040 delivered. But the supplier charges $180 for a finished sample, and the buyer budgets $240 for an internal fit and load test. The first order would save just $60 if the sample passes.

Now check the calendar. Suppose the specified panels can arrive in five weeks. The alternate sample needs one week to arrive, testing takes one week, and production and delivery take four more weeks after approval. If the panels are needed at the end of week five, buy the specified version for this order. Evaluate the alternate separately for a later run rather than counting on an unapproved part to arrive early.

If the alternate passes, record the approved grade, drawing revision and test result on the purchase specification. Ask for a repeat-order quote before projecting annual savings: the sample charge may disappear, but the unit price and freight still need confirmation.