Before approving a winter ocean freight quote, ask the carrier or forwarder one question: Does the price include a charge that assumes U.S. maritime fees resumed in November? They did not. The United States extended its suspension of certain Section 301 maritime fees and equipment duties through 11:59 p.m. Eastern time on January 9, 2027. For a January shipment, get the base price and any conditional charge in writing.
What changed, and who is affected
The Office of the U.S. Trade Representative (USTR) proposed the two-month extension in its October 26, 2026, Federal Register request for comments on further suspension of the China maritime action. USTR adopted the extension effective November 9 in its November 10, 2026, Federal Register notice modifying the Section 301 action. The pause is in force, not a proposal. USTR said it would consider whether to extend it again or take other action before January 10.
The notice addresses two distinct costs. First, no party owes or accrues the covered fees on maritime transport services during the suspension. That matters to shippers reviewing a carrier’s proposed fee pass-through. It does not mean the carrier must lower its base freight rate or remove an unrelated terminal charge.
Second, the pause covers additional duties under this action on certain Chinese ship-to-shore cranes and other cargo-handling equipment. A terminal buying equipment should check the specific item with its customs broker. The notice is not a blanket tariff exemption for Chinese machinery or for goods shipped in a container.
Compare the price you can commit to
Hypothetical example: A U.S. importer needs 12 containers on the same route in early January. Forwarder A quotes $2,400 per container plus a $150 allowance labeled “possible maritime fee.” Forwarder B quotes $2,500 per container, fixed for the same service and shipment window. These are illustrative commercial prices, not government fee rates.
If A confirms in writing that the allowance is payable only if a covered fee actually applies, its total without the allowance is $28,800, versus B’s $30,000. If A instead bills the allowance regardless, its total is $30,600. That one term changes A from $1,200 cheaper to $600 more expensive. If the shipment slips past January 9, do not assume either outcome: check the policy then in effect and the quote’s adjustment clause.
Before issuing the purchase order
- Ask for the basis of each surcharge. Have the bidder distinguish its own commercial charge from a government fee and identify what evidence it will provide before billing a pass-through.
- Specify the trigger. If a bid spans January 10, ask which event controls a price adjustment. Do not assume that booking in December locks the rate for a later port call.
- For equipment, separate freight from duty. Ask the broker to identify the tariff heading, expected entry date and other duties included in the estimate. Keep the equipment calculation separate from any vessel-related charge.
When seeking another bid, give each bidder the same route, service dates and surcharge questions. Use the directory of U.S. companies to identify businesses to contact, then compare written commitments rather than assuming that two quotes labeled “all-in” cover the same costs.